Data Warehouse Lab Work 6
Merge DataMerge Data or Data Merging is the process of combining two or more sets of data into a single data set. This process is necessary when you want to analyze or process large amounts of raw data that are stored separately in various types of files, worksheets, or data tables. Before analysis, the data needs to be merged to facilitate and expedite the analysis or data processing. ModuleDownload Module 6 DatasetDownload Dataset
24th Mountain Forest Course 1st Field Aranyacala Nature Lovers Students
The course is one of the activities organized by Aranyacala Nature Lovers Students. Currently, Aranyacala manages six active courses, including Mountain Forest Course, River Rafting Course, Rock Climbing Course, Paragliding Course, Maritime Course, and Cave Exploration Course. Currently, the author is participating in the Mountain Forest Course as one of the official requirements to become a full membership of Aranyacala. [{"url":"https://cloud.zulma.id/Gallery/Blog/24th-Mountain-Forest-...
Information Technology Project Management Lab Work 8
Team PlannerTeam Planner is a feature in Microsoft Project that functions to organize team work (Human Resources) that has been previously entered in the Resource Sheet. Additionally, Team Planner will generate an analysis of resource usage, which can be analyzed graphically to determine whether the resources are experiencing cost increases (overallocated) or are in line with the available resources. Team Planner is also used to allocate and organize the job responsibilities of each employee ...
Breaking the Fast with Aranyacala Trisakti to Knit Eternal Brotherhood
Maintaining ties is an obligation in this blessed month. This Aranyacala iftar (breaking the fast) is quite lively with various interesting activities. Many experienced seniors in their fields share stories and experiences with other Aranyacala members. In addition, various other event activities are filled with interesting programs such as door prizes and so on. [{"url":"https://cloud.zulma.id/Gallery/Blog/Breaking-the-Fast-with-Aranyacala-Trisakti-to-Knit-Eternal-Brotherhood/1.jpg","al...
Information Technology Project Management Lab Work 7
Resource SheetResource Sheet is a feature in Microsoft Project that serves to determine the resources we have when working on a project. This feature can be used to manage the resources we have in completing a project. The Resource Sheet has columns containing information about the identity and size of resources, including the indicator column, resource name, type, material label, initial, group, max unit, and code. Here is an explanation of the columns and their use in each project operation...
Data Warehouse Lab Work 5
Connected to MySQLMySQL is a multi-threaded, multi-user SQL database management system (DBMS) software with around 6 million installations worldwide. Pentaho Spoon itself supports importing and exporting data through DBMS, and one of the supported DBMS is MySQL. In this lab, you are required to connect MySQL with Pentaho Spoon. Below are the datasets stored in SQL format, and you can also download the work module. ModuleDownload Module 5 DatasetDownload Dataset
Machine Learning Lifecycle Webinar
Machine Learning Lifecycle is a process or a series of steps that must be followed to leverage machine learning and artificial intelligence technology. In this webinar, we will explain how to create a good and proper Machine Learning system lifecycle, including activities such as Machine Learning System Design and Structuring Machine Learning projects in accordance with industry standards. Speaker: Azhar Rizki Zulma (Internship Data Scientist BISA AI) Event Schedule: Sunday, April 17, 2022, a...
Information Technology Project Management Lab Work 6
Task UsageTask Usage is a feature in Microsoft Project that allows you to schedule working hours for each task. It is adjusted based on the working hours for each day. Task Usage will be connected with Actual Work and Progress Bar, where the hour calculations in Task Usage will be calculated based on Actual Work to determine the details of how many hours the task in the project is completed. Task Usage is typically used to obtain detailed data on the project’s tasks, so that the data can be a...
Data Warehouse Lab Work 4
Structured TransformationStructured transformation is the systematic and structured conversion of the original data measurement scale into another form, making it easier to analyze variability in the data. The expected output is also in the form of cleaner and more structured data. In today’s practical session, we will perform a simple data transformation by combining header data with content data separately and changing the data format from CSV to Microsoft Excel format. You can download the...
Information Technology Project Management Lab Work 5
Progress BarThe Progress Bar is a feature in Project where it functions to calculate the number of completed work, activities, or tasks. For example, in a task, the Database Architecture process has reached 80% completion. The data of the completed task can be inputted into the relevant task using the Progress Bar feature. Actual WorkActual Work is a feature in Project that functions almost similarly to the Progress Bar, but with the note that Actual Work is adjusted based on the percentage o...








